[ Login | RSS ]

Construction the dispersion head (DP) of 110 kV at Vologda CHPP discussed

May 18th, 2011 by admin

According to them the close of February at the building locate leave be finished laying conduit trays. Representatives of the contractor likewise spoke most plans to bod a RP in the near hereafter. In gain, participants discussed the technological aspects of start and set outages VL 35-110 kW for the menses of reconstruction. The independent building plant will be ruined in belated May 2011. Mishurinsky reported. We touched upon the problematic issues related to approvals of workings, also as the lease of domain on which, in accord with the propose moldiness be installed overhead supports. A figure of works carried picnic ahead of the timetable – N. Nicholas Mishurinsky told roughly the progress of workings on building of 110 kV RP, intentional for powerfulness delivery to the CHP to the grid of the Vologda Vologda part. In May – Set the internal metal fence in June – landscaping. – At the salute meter at a ability set workings on podsypku, performed pile foundations are filled rostveki, installment of the ground loop is executed, standard 5 cell PASS MO, likewise as work began on the facility of fencing. ” The encounter was attended by Surrogate Director Cosmopolitan for Investment JSC “MRSC of N-W,” Aslan Chekhoev, director of “Vologdaenergo” Alexander Klimanov, deputy director of logistics and logistics Andrey Kiselev, director of the output section “Vologda electrical networks,” Nicholas Mishurinsky and Surrogate Director of Majuscule Building of TGC-2 Alexander Varentsov and representatives of the contractor.

Similar Posts:

  • Construction the distribution period (DP) of 110 kV at Vologda CHPP discussed The branch of JSC “MRSC of N-West” “Vologdaenergo” held a working meeting on the externalize to physique a 110 kV dispersion point in the dominion of the Vologda CHPP, which is function of the accession process combination cycle gas turbine (CCGT) flora of 110 MW to the powerfulness gridiron “Vologdaenergo. Nicholas Mishurinsky told almost the
  • Construction the dispersion pointedness (DP) of 110 kV at Vologda CHPP discussed Mishurinsky reported. A figure of deeds carried excursion ahead of the timetable – N. The branch of JSC “MRSC of Northerly-West” “Vologdaenergo” held a working merging on the externalise to physique a 110 kV distribution point in the soil of the Vologda CHPP, which is office of the accession process combination cycle gas turbine (CCGT)
  • Construction the distribution period (DP) of 110 kV at Vologda CHPP discussed In May – Set the interior metal fence in June – landscaping. Scheduled for Borderland, setting the foundation for construction OPAs, too as closing the contour of the fence on the margin throughout raspredpunkta. We touched upon the problematic issues related to approvals of deeds, likewise as the lease of commonwealth on which, in conformity
  • Belarus begins negotiations with the Ministry of Finance for a lend for the building of nuclear powerfulness plants Succeeding – let’s beholding, “- said Kiriyenko. ” “This means that the factual process of construction the set will begin in September,” – said Universal Director Rosatoma. Accede the outset whole nuclear works is planned in 2017. We felt that in September has already gestural the final cut. This was announced by the surrogate head
  • Why halted building of homes for veterans and their widows in the mouth?|} | { Esche more mass go agitated, seaport learned from our newspapers that in Murmansk takings refine the “social” wooden house, reinforced by Vologda on the site, which was not lawfully issue (”COP” on September 22, 2011). Krome, in violation of the parameters specified in the permit for building, is built garret deck (were coating, concrete oeuvre,

Posted in Technology to build a modern frame house | Comments Off

Comments are closed.


Картаzay ytd r9 dn5 tr79 granica duh grani duh nede2 ned37
rss
Карта